Cryogenic gas processing sits in a category of its own. These plants operate at temperatures well below -150°F (-101°C), and many core steps push toward the boiling point of liquid nitrogen at roughly -320°F (-196°C).
There are various hazards in those conditions: exposed skin can freeze almost instantly, common alloys turn brittle, and equipment has to survive violent thermal swings.
Building facilities that chill natural gas into liquefied natural gas (LNG), generate liquid nitrogen, or recover natural gas liquids (NGLs) isn’t just technically hard. However, it’s capital-intensive, tightly regulated, and a single mistake can cost millions.
Why Start a Cryogenic Plant?
Why do it? Because cryogenic plants do things nothing else can. LNG facilities cool pipeline gas to about -260°F (-162°C), shrinking it to roughly 1/600 of its normal volume so it can be shipped worldwide and later regasified for pipeline use.
Air separation units (ASUs) distill atmospheric air into oxygen, nitrogen, and argon. That oxygen may supply hospitals, while the nitrogen feeds semiconductor fabs — which expect purity in the 99.99% to 99.999% range.
NGL recovery units pull ethane, propane, butane, and heavier hydrocarbons out of raw gas streams and turn them into petrochemical feedstocks, heating fuels, and blending components.
In other words, these plants keep energy logistics, medical supply chains, and advanced manufacturing moving.
High Stakes, High Commitment
Because the stakes are that high, most owners don’t split design, procurement, and construction across multiple firms and hope it all fits together.
They use an EPC delivery model: Engineering, Procurement, and Construction; services delivered by PLC Construction.
So one party owns the entire path from concept through startup and can be held accountable for performance.
That EPC path covers five phases:
- Concept development
- Front-End Engineering Design (FEED)
- Detailed engineering and procurement
- Construction and installation
- Commissioning and startup
Getting each phase right is the difference between a plant that starts cleanly and one that needs months of rework.
Why EPC Matters More for Cryogenic Plants
In conventional gas projects, you can sometimes hand off design to one firm, buy equipment through another, and let a third party build it.
In cryogenic service, there are dangers. At cryogenic temperatures:
- Carbon steel that behaves fine at ambient can fracture like glass.
- Seals that work warm can leak when cycled cold.
- Piping grows and shrinks as systems warm for maintenance and then plunge back to operating temperature.
If design, purchasing, fabrication, and installation sit with different groups, small mismatches can surface only at startup.
EPC tightens that chain.
One team sets requirements, vets vendors, oversees fabrication tolerances, manages site installation, and then has to prove the plant runs. That continuity is why EPC is standard for LNG trains, ASUs, and similar deep-cold systems.
Phase 1: Concept Development and Feasibility

This first phase answers the blunt questions before major capital is committed.
- Is there durable market demand?
- Can we permit and build where we want?
- Will the economics survive changes in feedstock or power cost?
Market analysis is essential to understand the underlying requirements.
For LNG, can you lock in long-term offtake?
For industrial gases, do nearby end users — hospitals, fabs, refineries, chemical plants — have enough steady demand to justify capacity?
A design that works in a Gulf Coast energy hub with dense pipeline access and cheap power may fail in a region with limited infrastructure.
Site selection becomes a discipline of its own. Cryogenic plants need:
- Pipeline or product tie-ins
- Serious electrical capacity
- Heavy-haul access for oversize equipment
- Physical stand-off from neighborhoods
- Local emergency response familiar with cryogens
That last point is not optional. Cryogenic liquids like nitrogen boil at roughly -320°F (-196°C), expand rapidly as they warm, and can displace breathable oxygen, creating an asphyxiation hazard in enclosed or low-lying areas.
First responders and plant operators both need to understand how fast an oxygen-deficient atmosphere can develop.
Product specification also gets locked here. A 500-ton-per-day oxygen plant is not just a scaled-up 50-ton unit. It’s different compressors, different power demand, different logistics.
Purity targets drive cost. Supplying generic nitrogen for pipeline purging is one thing. Supplying ultra-high-purity nitrogen to a semiconductor fab — which treats contamination as a line-stopping event — is something else entirely.
Permitting starts in this phase, too. Environmental impact assessments, air permits, noise studies, dispersion modeling. Those timelines are measured in months, sometimes quarters.
Waiting until detailed design to talk to regulators is how you lose a year.
Looking for an EPC Company that does it all from start to finish, with in house experts?
Phase 2: Front-End Engineering Design (FEED)
FEED turns a commercial idea into an engineering definition. Process engineers simulate refrigeration cycles, column performance, compression stages, and energy balances. The goal is to lock in a flow scheme that can actually deliver capacity and purity at a realistic power load, not just on paper but in steel.
Key FEED outputs include:
- Process flow diagrams (PFDs)
- Piping and instrumentation diagrams (P&IDs)
- Preliminary equipment data sheets
- Plot plans and layout concepts
- An early project schedule and cost estimate tied to real equipment, not guesses
For cryogenic plants, FEED also runs structured safety reviews.
HAZOP teams spend hours walking “what if?” paths:
- What if a valve fails during cooldown?
- What if power dips mid-restart?
- What if nitrogen leaks into an enclosed work area and drives oxygen below safe breathing levels?
By the end of FEED, owners usually make the final go/no-go decision. After that, the project stops being “an idea we’re studying” and becomes “an asset we’re going to build.”
Phase 3: Detailed Engineering and Procurement
Detailed engineering takes FEED and turns it into construction documents. Every pipe size, cable run, support, foundation, and instrument loop gets defined. At cryogenic temperatures, those details decide whether the plant runs.
Thermal movement is a big one. A line that’s 100 feet long at ambient can pull in by several inches once it’s cooled toward cryogenic service.
If you don’t design flexibility the line can crack or tear away from its supports. This is where expansion loops, spring supports that allow movement, and materials that stay ductile in the cold are taken into account.
Structures and platforms also have to handle shifting loads as systems fill, empty, warm, and cool.
Procurement in this phase often dictates the schedule. Cryogenic hardware is not commodity gear. Cold boxes, plate-fin heat exchangers, and large cryogenic compressors come from a short list of qualified manufacturers worldwide.
Lead times can run 12–24 months, and the quality requirements are unforgiving: welds get 100% radiography, helium leak tests are standard, and low-temperature impact toughness must be proven, not assumed.
Miss a spec and you’re not just slipping startup, you might be arguing warranty instead of making a product.
The EPC contractor’s job here is to lock in suppliers early, audit their shops, and align deliveries with the construction plan. Getting a 200-ton cold box six months late can idle an otherwise finished site.
Phase 4: Construction and Installation

Field work on a cryogenic plant is not typical pipe-rack construction. Crews pour deeper foundations and install insulation barriers because cryogenic service can supercool surrounding soil and damage supports. Anchor bolts and supports use alloys selected to stay ductile at very low temperatures, not snap like glass. Rigging plans for cold boxes read like surgery notes because a dented shell can ruin vacuum integrity and cripple performance.
Where possible, teams lean on modularization. Skids — pumps, valves, instruments, wiring — are assembled and tested in controlled shop conditions, then shipped and tied in. That improves quality, reduces weather risk, and shortens field work.
Safety training during construction reflects cryogenic realities, not just generic industrial hazards. Workers are trained on two critical risks:
- Oxygen displacement. Boiled-off nitrogen or similar gases can drive oxygen below safe breathing levels without obvious warning.
- Extreme cold. Liquid nitrogen around -320°F (-196°C) can cause instant frostbite, and materials embrittled by cold can fracture violently. hvcc.edu+1
Before introducing any cryogenic fluids, the team runs mechanical completion checks: pressure tests, vacuum integrity checks, helium leak tests, and full instrument loop checks back to the control system. Finding a wiring or torque issue now is cheap. Finding it during cooldown is not.
Phase 5: Commissioning and Startup
Commissioning is when the site stops being a construction project and becomes an operating asset. Systems are brought online in a controlled sequence, instrumentation is proven, and operators rehearse logic, shutdowns, and emergency responses.
Cooldown is the make-or-break step. You cannot shock-freeze a cryogenic unit. Temperature has to drop in a controlled profile so metal, welds, seals, and instruments adjust without cracking.
Operators watch temperature points across exchangers, columns, and piping, looking for uneven cooling that hints at blockage or trapped moisture. Rushing this stage is how expensive equipment gets damaged before the first product ever ships.
After cooldown, performance testing answers the only question that really matters:
- Does the unit hit purity and capacity at the energy use predicted in FEED?
- If not, is the issue tuning, or is it mechanical?
Startup teams also clean up instrumentation quirks like transmitter drift and incorrect level readings at deep-cold temperatures.
What Separates Successful Cryogenic EPC Projects
Certain patterns show up again and again on projects that start up cleanly and stay reliable:
Experienced people. Engineers who’ve designed multiple cryogenic units catch material and flexibility problems early.
Construction managers who’ve set cold boxes know the difference between “good enough” and “this will fail at -260°F.” Operators who have brought similar systems down and back up treat cooldown like a controlled sequence, not a race.
Early risk work. Technical risk (Can this vendor really meet cryogenic specs?), schedule risk (Are long-lead items ordered in time?), and operational risk (Do we have procedures and training for oxygen-deficient atmospheres and extreme cold exposure?) get attention from day one.
Tight communication. Weekly project reviews clear clashes before they turn into rework. Regular updates with regulators keep permits moving.
Local outreach matters too; emergency responders need to understand what a cryogenic release looks like and why oxygen displacement is so dangerous.
Technology, Compliance, and the Finish Line
Most owners lean toward proven core technology because long-term reliability usually beats a tiny efficiency gain nobody has field-proven at scale. Digital layers, though, are no longer optional.
Predictive analytics spot performance drift in compressors and cold boxes before it becomes downtime. Advanced process control helps hold purity and throughput on spec. Remote monitoring lets senior specialists support field operators in real time.
Compliance is not paperwork theater. Industry codes like ASME Section VIII (pressure vessels), API 620 (low-temperature tanks), and NFPA 55 (compressed gases and cryogenic fluids) define safe design, storage, handling, and oxygen-deficiency prevention for cryogenic and compressed gas systems.
Ignoring those standards isn’t just illegal; it invites denied permits, higher insurance exposure, and preventable safety incidents. Environmental requirements around air emissions, vented gas, noise, and stormwater also have to be designed in early; bolting them on late is how schedules fall apart.
Bringing It Together
Cryogenic gas plants are unforgiving. You’re dealing with fluids near -260°F to -320°F (-162°C to -196°C), handling products whose volume, purity, and reliability underpin global energy logistics, hospital supply chains, and modern semiconductor manufacturing. The margin for error is thin.
The five-phase EPC path gives structure to that risk: Concept → FEED → Detailed Engineering & Procurement → Construction → Commissioning/Startup.
The winners are the teams that treat each step with discipline: realistic siting and permitting, serious FEED work that bakes in safety and operability, early procurement of long-lead cryogenic hardware, field execution that respects what extreme cold can do, and a controlled startup led by people who’ve done it before.
Teams that follow that model don’t just reach the first product. They hand over plants that hit spec, run reliably, satisfy regulators, and protect people. In the cryogenic world, that’s the difference between an asset and a liability.
PLC Construction provides complete EPC services, comes with decades of expertise, works with skilled and certified professionals, and has the experience to back it up.

Dan Eaves, PE, CSE
Dan has been a registered Professional Engineer (PE) since 2016 and holds a Certified SCADA Engineer (CSE) credential. He joined PLC Construction & Engineering (PLC) in 2015 and has led the development and management of PLC’s Engineering Services Division. With over 15 years of hands-on experience in automation and control systems — including a decade focused on upstream and mid-stream oil & gas operations — Dan brings deep technical expertise and a results-driven mindset to every project.
PLC Construction & Engineering (PLC) is a nationally recognized EPC company and contractor providing comprehensive, end-to-end project solutions. The company’s core services include Project Engineering & Design, SCADA, Automation & Control, Commissioning, Relief Systems and Flare Studies, Field Services, Construction, and Fabrication. PLC’s integrated approach allows clients to move seamlessly from concept to completion with in-house experts managing every phase of the process. By combining engineering precision, field expertise, and construction excellence, PLC delivers efficient, high-quality results that meet the complex demands of modern industrial and energy projects.