    South Eddy Gas Plant

    Project Value: $6 million
    Owner: Enterprise Products
    Project Duration: Dec 2015 – May 2016
    Statistics: HOURS 59,732 / TRIR 0.00

    PLC Construction, Inc. was awarded the I&E construction portion of the South Eddy Gas Plant, a 230MMSCFD Cryogenic Gas Plant in New Mexico. PLC Construction’s scope was to provide all labor for construction, loop checks and commissioning.

    PLC mobilized a crew of craftsmen that averaged 100 people. This was a mixture of New Mexico State licensed electricians, instrument technicians, and instrument fitters. Our electrical construction crew also performed the all task associated with the install and commissioning of the gas plant.